In
2003:
- Wetland
acres increased to approximately 1,561 due to efforts by the Seven Mile
Creek Clean Water Partnership Project to restore an additional 128 acres;
the restoration was funded through the CRP-based Farmable Wetlands Program;
- An adjacent
drainage tile was routed into the wetlands to improve water quality
and to hold back water;
- Talks
to improve County Ditch (CD) 29 increased; and
- Overson
Lake was targeted for potential restoration to offset drainage improvements
to CD 29.
In 2004:
- Landowners
and farmers proposed improvements to drainage of the old, undersized
CD 29 system; and
- Talks
began between watershed project managers and petitioners to offset any
increase in peak flow in Seven Mile Creek by stabilizing the downstream
bank near CD 13 and Highway 99, as well as possibly restoring Overson
Lake to a wetland. Next
|
|
|